Capital Cost Estimate Outputs Capital Cost estimates will be reported as a range by FRA SCC for each of the preferred routes ■ The high-cost estimate includes an additional 30% unallocated contingency over and above the low-cost estimate to account for unforeseen circumstances that impact project delivery. ■ The values will represent high-level cost estimates to support early planning. ■ Substantial additional planning and analysis would be required for further refinement and accuracy. FRA SCC SCC 10: Track Structures & Track SCC 20: Stations and Terminals SCC 30: Support Facilities: Yards, Shops, Admin. Bldgs. SCC 50: Communications & Signaling SCC 70: Vehicles SCC 80: Professional Services Total U.S. Department of Transportation Federal Railroad Administration 146 FRA LONG-DISTANCE SERVICE STUDY