Investor Presentaiton
JINDAL
STEEL & POWER
Major projects' timeline
Angul Phase II: Disciplined capex approach over next
5 years
FY22
Angul Pellet Plant #1: 6MTPA
FY23
Angul Pellet Plant #2: 6MTPA
Slurry Pipeline
HSM Phase #1: 3MTPA
HSM Phase #2 Expand to 5.5 MTPA
FY24 & onwards
Expected
COD
Sep 22
Sep 23
Sep 23
Feb 23
Sep 23
Blast Furnace #2: 4.25 MTPA
Dec 23
Angul BOF #2: 3.3 MTPA
Dec 23
DRI #2: 2.7 MTPA
Angul EAF #2 : 3 MTPA
Feb 25
Feb 25
Oxygen plant, Coke oven, RMHS
Sep 23
Margin Expansion Projects (Total capex: USD 888 mn)
Capacity Expansion Projects (Total capex: USD 1,532 mn)
Expansion Capex (USD Mn)
322
FY22 (P)
632
578
551
FY23 (P)
FY24 (P)
FY25 (P)
336
FY26 (P) & FY27
(P)
U.S.$1.00 = 74.2551, which was the exchange rate as reported by the FBIL on September 30, 2021.
On the back of strong cash flows, JSP Group has announced a round
of growth capex to propel its steel capacity from 9.6MT to 15.9MT
(+66%) through brownfield expansion
■The 6.3MT expansion is proposed at a modest capex of c.
US$400/t, among the lowest in the industry, driven by its Blast
Furnace and Electric Arc Furnace
■The expansion also includes investment in cost saving projects
like pellet plant, slurry pipeline, etc.
The projects, which are expected to increase steel capacity by 66%
and pellet by 133%, will be commissioned in a modular fashion from
Sep 2022 to Feb 2025, thereby largely self-funding the cash flow
needed for the capex
24