Palo Verde Nuclear Generating Station Ownership and Leases
MW Owned vs Leased
Unit 1
Unit 2
Unit 3
Owned
Leased
2.3%
7.9%
30 MW
Owned
9.5%
124 MW
Owned
10.2%
134 MW
104 MW
Leased
Total
10.2%
134 MW
Total
0.7%
10.2%
10 MW
134 MW
Leased
0%
0 MW
Total
10.2%
134 MW
Yearly Payment Amounts
■ Total PV Unit 1 - $16.5M
■ Total PV Unit 2 - $1.6M
Lease Expiration and Replacement
⚫ June 11, 2020: PNM gave irrevocable notice to return leased assets upon expiration of the extended
leases on January 15, 2023 (Unit 1) and January 15, 2021 (Unit 2)
•
April 2, 2021: PNM filed for abandonment and replacement of leased capacity
• 450 MW solar PPA, 290 MW storage ESA
⚫ August 25, 2021: NMPRC deemed abandonment previously approved
•
February 16, 2022: NMPRC approved proposed replacement power
PNMResources