Capacity Enhancement and Sales Trend
12
Significant/Proposed Capacity Enhancement
Capex (in Rs. Mn.)
Products (Location)
Existing
Capacity
Capacity Addition
Capacity After
Expansion
Total
Already
incurred
Balance to
be incurred
Specialized Products
DI Pipes
240,000 TPA
420,000 TPA
660,000 TPA
4,000
681
3319
Ferro Alloys
130,000 TPA
60,000 TPA
190,000 TPA
1,500
815
685
Others
Revamping Existing
Blast Furnaces
509,250 TPA
240,750 TPA
750,000 TPA
2,500
1128
1372
(Unit III)
Sinter
608,000 TPA
600,000 TPA
1,208,000 TPA
1,100
774
326
(Unit III)
BFG Boiler
(Unit IV)
0.00 TPH
35 TPH
35 TPH
300
25
275
Misc De-Bottle Necking
TOTAL
600
385
215
10,000
3,808
6,192
Current Status
JBG
Will be done in 2 phases - Phase 1 = 2Lac
T expected to commission by FY24; Phase
2: = 1.5 Lac T expected to commission by
FY25
Will be done in two phases- Phase 1 around
36000 TPA to be commissioned by FY24
and Balance will be commissioned by FY25.
1 furnace is under process and is expected
to be commissioned by FY24. 2nd furnace
will be completed in next FY
Will be done in 2 phases; In process of
setting up 1st phase of the same during
current FY and 2nd phase shall be
commissioned in FY25
This is a green energy project which aims to
reduce carbon footprints. Plan is to add this
in captive power plant for optimizing|
utilization of waste gases from BF
Includes backward integration to sinter
Plant, Upgradation of PCI and Oxygen plant
for cost cutting of producing Hot metal from
Pig iron Plant.View entire presentation