US-ABWR Spent Fuel Pool Cooling During SBO ■Fuel Pool Cooling and Cleanup (FPC) system is available if connected to CTG ■ With no FPC, under the maximum abnormal heat load with the pool gates closed, pool will boil in approximately 16 hours - Provides sufficient time for operator to connect fire hoses for pool make-up Without make-up water the fuel will remain covered for approximately 77 hours ■Permanent redundant plant pipe installed at opposite ends of the RB with external temporary connections to allow hook up for make-up water to spent fuel pool ■Diesel-driven Fire Protection System (FPS) pump capable of supplying water to pool via RHR and FPC piping TOSHIBA Copyright © 2012 Toshiba Corporation. All rights reserved. Leading Innovation >>> 27