NVE 2021 Integrated Resource Plan
⚫ June 2021 IRP filing; decision expected by year-end 2021
―
-
-
Seeks approval of two NV Energy-owned solar/battery projects to facilitate retirement of
coal-fueled North Valmy Generating Station
O Iron Point solar project: 250 MWs, 200 MWs battery storage
O Hot Pot solar project: 350 MWs, 280 MWs battery storage.
Acquisition of 19.5 MW Fort Churchill solar facility, currently leased from Apple
Addition of 146 MWs of turbine upgrades to be in-service by summer 2022; Public Utilities
Commission of Nevada (PUCN) approved September 2021 for expedited execution
Modifies load forecast methodology to reflect warming trend; 16% planning reserve margin
Ongoing proceedings for new renewable energy/storage projects and energy efficiency plan
Includes distributed resource plan with implementation of distributed energy resource
management system, and a trial NV Energy-owned rooftop solar with storage program
September 2021 - IRP filing amendment
-
―
Transmission infrastructure for a clean energy economy plan filed with the PUCN as part of
2021 triennial joint IRP, pursuant to Senate Bill 448
Plan seeks approval to proceed with slightly over $1 billion construction of Greenlink North
and the Harry Allen to Northwest segment of Greenlink West to be completed by December
2028