Investor Presentaiton
Azov Wind Farm: approaching final stage of
construction despite COVID-19 challenges
Challenges caused by pandemics
COVID-19 cases on the
construction site
impact on the entire
manufacturing chain
travel restrictions to enter
Russian territory from
abroad
temporary
interruptions of works
issues with supply and
delivery of several main
components
issues with arrival of
foreign specialist and
supervisors
enel
Project's current status
HV T-line, done 50 km out of 50 km (290 towers)
MV collector system, done ~ 15 km out of 15 km
Internal Roads, done ~ 16 km out of 16 km
2
WTGs foundations, done 26 units out of 26
Delivery of main wind turbine components
completed
Wind turbine installation works are at final stage
20 out of 26 WTGs placed
HV Substation fine-tuning tests under finalization