Azov Wind Farm: approaching final stage of construction despite COVID-19 challenges Challenges caused by pandemics COVID-19 cases on the construction site impact on the entire manufacturing chain travel restrictions to enter Russian territory from abroad temporary interruptions of works issues with supply and delivery of several main components issues with arrival of foreign specialist and supervisors enel Project's current status HV T-line, done 50 km out of 50 km (290 towers) MV collector system, done ~ 15 km out of 15 km Internal Roads, done ~ 16 km out of 16 km 2 WTGs foundations, done 26 units out of 26 Delivery of main wind turbine components completed Wind turbine installation works are at final stage 20 out of 26 WTGs placed HV Substation fine-tuning tests under finalization 3 https://youtu.be/HK-gg6 10-s