NHPC Financial Highlights & Renewable Energy Projects
NHPC -JV Projects Under Clearance
S.No
Projects
Installed
Capacity (MW) Energy (MUs)
Design
Cost (In Cr.) &
PL
1
Kirthai-Il
930
3330
(6x140 + 2x35 + 2x10)
UT of J&K
6384
(Feb'20)
Total
930
3330
6384
Status
33
एनएचपीसी
NHPC
•MOU has been signed between NHPC Ltd. and JKSPDCL on
03.01.2021.
•The project shall be executed by M/s CVPPPL on the same terms
and conditions of that of Pakaldul, Kiru & Kwar H E Projects.
•The Appraisal has been transferred in the name of CVPPPL by CEA
on 29.12.2021.
⚫Defence Clearance was accorded by MoD on 24.03.2022.
• Extension of validity of appraisal up to 13.06.2024 was accorded
by CEA on 29.08.2022. Balance investigation works are in progress
in compliance to DPR concurrence.
⚫EAC had recommended for grant of Environment clearance (EC)
to the project on 15.04.2021. MOEF vide letter dated 24.5.2021 has
intimated JKSPDC that EC shall be accorded after Stage-l Forest
Clearance is granted.
Application for FC on Parivesh Portal of MOEF&CC submitted
successfully on dated 19.10.2022View entire presentation