Expansion Plans and Financial Overview
Expansion Plans
Increase In Cement Capacity by 5.5 MTPA
-
JKCement
A) Existing Units – The Cement capacity of Mangrol, Muddapur, Jharli & Aligarh
Units would be increased by 0.5 MTPA each by various modifications .Thus overall
capacity of existing units would be increased by 2 MTPA i.e. from 14.67 MTPA to
16.67 MTPA.
-
B) Split Grinding Unit – New SGU having capacity of 1.5 MTPA would be set up in
Ujjain .
In Wholly owned Subsidiary Jay Kay Cem (Central) Ltd –
C) Clinker Capacity at Panna M.P - Clinker capacity at Panna would also be increased
by 0.66 MTPA to meet out incremental clinker requirement.
D) Split Grinding Unit – New SGU having capacity of 2.0 MTPA would be set up in
Prayagraj.
The overall Cement Capacity of 5.5 MTPA would be implemented in phased manner in
next two years with a total capital cost of Rs 1161 crores. (US$26 per tonne)