Australia Coal and Laos Power: Operational and Financial Summary slide image

Australia Coal and Laos Power: Operational and Financial Summary

Australia coal: quarterly equity ROM output Total equity ROM (Mt) LW move Mandalong (100%) Springvale (50%) ACTUAL PLANNED (INDICATIVE ONLY) BANPU 5.0 4.3 4.5 3.0 3.8 4.0 3.2 3.3 3.1 3.3 3.5 2.5 3.0 2.5 2.2 2.5 1.6 2.1 1.8 2.0 2.2 1.7 1.1 1.5 1.0 1.8 1.4 1.4 1.4 1.6 0.5 1.0 1.2 1.5 0.0 1Q15 2Q15 3Q15 4Q15 1Q16e 2Q16e 3Q16e 4Q16e 2015 2016e Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 3 wks 6 wks Awaiting Approvals 3 wks Normal production 31 wks 3 wks Bolt-up/commissioning 2 wks LW relocation Note: 1. Bar width is indicative of the equity production contributions to Centennial 2. Production generally responds to the timing of longwall changeovers (i.e. lower production results during a longwall changeover period) 3. Angus Place was put on care and maintenance from February 2015. NORTHERN WESTERN 49 67