Post-ISA • Construction ● • RIE construction and Customer construction • Municipal inspection is required during construction Rhode Island Energy™ a PPL company At the conclusion of construction prior to interconnection, there is a Witness Test (WT) This ensures that the system is programmed correctly and operates as expected Meter will be set after the conclusion of the WT All systems 25 kW and above will be registered with ISO-NE Systems 5 MW and above will be fully dispatchable by ISO-NE BUSINESS USE ORhode Island Energy 11