Investor Presentaiton

Investment Programme • - - Regulatory baseline cost of £3,144m (14/15 prices) was based on management's detailed assessment of cost Direct Works of £1,855m (Main Works Contractors, System Integrator and Programme Wide) Indirects of £669m (resources, insurances, facilities, IT) Contingency of £526m Annual profile reflects regulatory baseline construction programme £m 2014/2015 prices Regulatory baseline cost, annual profile 600 500 390 400 531 519 497 407 Illustrative management build up to regulatory baseline cost 2014/2015 prices Contingency, £526m 300 266 238 200 Handover and Acceptance_ period, £94m 100 117 83 38 30 28 0 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Indirects, £669m Programme Wide, £63m West, £421m System East, £605m Integrator, £25m Regulatory funding baseline derived from robust bottom-up estimate Central, £741m 10