IEC Transmission Segment Development Plan 2023-2027 slide image

IEC Transmission Segment Development Plan 2023-2027

The IEC Transmission Segment Development plans for 2023-2027 in the transmission segment ■ Addition of appx. 738 circuit km ultra-high voltage transmission lines (400 KV). ■ Establishment of appx. 930 circuit km high voltage transmission lines (161 KV). חברת החשמל Israel Electric Upgrading of appx. 989 circuit km of existing network (high voltage poles) and re-construction of appx. 462 circuit km. ■ Addition of appx. 155 km underground cable circuits. ■ Construction of 3 new switching stations so that by the end of 2025, the total expected capacity in existing and new 400/161 KV switching stations will be 17,695 MVA. ■ As of the end of 2022, the company has at it's disposal 149 substations with total capacity of 19,486 MVA. ☐ By the end of 2025, the total capacity of the substations is expected to reach 24,849 MVA. Source: IEC's Financial reports for 2022FY Investor Relations 24 24