Property Marketing and Sales Review

Commitment to deliver new 2020 projects Cendana Peak - started construction in 4Q20 Road works Jun 21 Target Launched 2020 completion Estimated SOLIPPO PT LIPPO KARAWACI TOK 3Q21 Total residential units construction 328 $5 mn costs to completion Total GFA 22,863 sqm Cendana Peak Sep 21 % Sold as per 30 Sep 2021 100% SOHO at Fairview Tower - started construction in 2Q20 SoHo Jul 21 Launched 2020 Target completion 3Q21 Estimated Total residential units construction 91 $3 mn costs to completion % Sold as Total GFA 6,601 sqm Sep 21-ready for handover per 30 Sep 2021 39% Note: USD/IDR exchange rate for construction cost to completion in 9M21 refers to the average rate between 30Jun21 to 30Sep21 at Rp14,429 15