NHPC Renewable Energy and Pump Storage Project Updates slide image

NHPC Renewable Energy and Pump Storage Project Updates

Renewable Energy A (ii) Standalone (As Intermediary Procurer) (a) Under Construction एनएचपीसी NHPC 22 Capacity S.No Name of Project (MW) Estimated Capital cost (in Crs.) Expected Commissioning Tariff (Rs./unit) Status of PPA Schedule 1 Projects through Solar 2000 Power Developers, Rajasthan 0.00 Total-(a) 2000 0.00 2024-25 (Out of 2000 MW, 320 MW capacity was awarded to M/s Avaada Sunrays Energy Pvt. Limited which has been commissioned on 10.12.2022. Further, Balance capacity of 1680 MW is expected to be commissioned by 2024-25) 2.55 (1680MW) PPA and PSA signed. 2.56 (320 MW) Tariff adopted by CERC