Optimising maintenance
ARAM1 is a multi-year transformation program improving maintenance strategies, planning and
execution, driving improved asset availability and reliability
HUNTER VALLEY ROLLINGSTOCK CANCELLATIONS
40
anes:
30
50
20
20
10
May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21
Jilalan wagon overhaul facility
0
CASE STUDY: 2800 CLASS COMPONENT CHANGE OUT (CCO) AT STUART DEPOT
Traditional overhaul
•
Broad scope & long duration
Fixed time interval
•
Early & more frequent change out
of components
CCO
•
.
Scope & timing align with condition
Component change spread over
multiple intervals
Longer component life
Average 10-15% reduction in locomotive
overhaul costs for 2800 class
Average 25% reduction in loco downtime
in overhaul - improved asset availability
1. Above Rail Asset Management
CCO Engine Change at Stuart depot