Supa dustrial Area (Japanese Industrial Park): Infrastructure Road & Connectivity ■ All internal roads of SUPA have been completed (17 kms and 7.5 meter wide) MAGNETIC MAHARASHTRA 2.0 #MadeForBusiness Water Availability ■ 2 Million Liter per Day (MLD) available ■ 13 MLD of water will be made available for industries from March 2021 ■ Centralized Waste-Water Treatment with maximum capacity of 63 MLD in Ahmednagar Power Availability ■ Power for Construction is available at 11 KV Voltage Level ■ Power supply network of 33kv/11kv Sub Station with two 10 MVA (10,000 KVA) transformers has been completed ■ 11 KV power supply along with distribution transformer center will be completed by June-2021 ■ 33 KV switching sub- station with 6 outgoing 33 KVs express/ non express feeder will be completed by June - 2021 Streetlights ■ Streetlights are operational since January 2019