Supa dustrial Area (Japanese Industrial
Park): Infrastructure
Road & Connectivity
■ All internal roads of SUPA have been completed (17 kms and 7.5 meter wide)
MAGNETIC
MAHARASHTRA 2.0
#MadeForBusiness
Water Availability
■ 2 Million Liter per Day (MLD) available
■ 13 MLD of water will be made available for industries from March 2021
■ Centralized Waste-Water Treatment with maximum capacity of 63 MLD in Ahmednagar
Power Availability
■ Power for Construction is available at 11 KV Voltage Level
■ Power supply network of 33kv/11kv Sub Station with two 10 MVA (10,000 KVA) transformers has been completed
■ 11 KV power supply along with distribution transformer center will be completed by June-2021
■ 33 KV switching sub- station with 6 outgoing 33 KVs express/ non express feeder will be completed by June - 2021
Streetlights
■ Streetlights are operational since January 2019View entire presentation