Khemisset Project Investment Highlights
ONGOING SITE WORKS TO SUPPORT BASIC ENGINEERING
KHEMISSET
PROJECT
EMMERSONPLC MSLMINERALS.
KHEMISSET
PROJECT
Deep Drilling (Decline Alignment) Campaign
The drilling campaign of 200m (DA-1), 400m
(DA-2), 1,200m (DA-4), 2,000m (DA-6) &
3,200m (DA-9) has now been completed.
Therefore, the first stage of the
Geotechnical Geological drilling campaign
for decline alignment has been finished.
Surface/Shallow Geological Investigations
This program has finished. The campaign
included 20 shallow drillholes with SPT
(Standard Penetration Test) and detailed
sampling for testing program: 17 CPT
(Cone Penetration Test) and Electrical
Resistivity Tomography survey for analysis
of surface geology.
Core Logging, Testing & Storing
Local to the site, there is a well managed
and maintained core store where each
sample is taken for logging, testing and
storing. This is an ongoing operation and
the value added to the project at this facility
is immeasurable.
18View entire presentation