Nova Capitalised Development Costs
Variance
Actual Budget(1)
Area
A$M
A$M
A$M(2)
%
Process Plant
161
176
(15)
(9%)
Non-mine Infrastructure
90
99
(8)
(8%)
Mine Development
64
55
10
18%
Mine Infrastructure
46
46
n/a
Pre-operating Costs
134
75
59
79%
less capitalised revenue
(39)
(7)
(32)
459%
Total
456
443
13
3%
Nova
Capital expenditure reconciliation
igo
3% variance from uninflated January 2015 budget
estimate is a great result
• Demonstrates a good overall discipline in cost
management
Actual spend is 4% or A$17M lower than feasibility study
estimate
Actual cost includes additional unbudgeted
expenditure
Additional underground development
Process plant equipment changes to provide
debottlenecking opportunities
Additional water supply exploration and development
Longer period of pre-commercial production expenditure
1) Uninflated January 2015 revised budget (Initial July 2014 Feasibility
Study estimate of A$473M revised down to A$443M in January 2015)
2) May not add up due to rounding