Investor Presentaiton
ANNUAL REPORT
P
Private Power and Infrastructure Board
ANNUAL REPORT
Private Power and Infrastructure Board
As envisioned by the GoP, this initiative rightly served the purpose and as an outcome, three mega
imported coal based plants namely Sahiwal, Port Qasim and Hub Power were inducted into the system
within the average period of less than 4 years. Progress journey of these mega projects under the
efficient and vigorous facilitation by PPIB starting from issuance of LOI to commissioning is illustrated
as follows:
Project Name
Date of LOI Date of LOS Date of FC Date of COD
Total Time
(Months)
Sahiwal
21.05.2014
17.04.2015 31.03.2017
28.10.2017
41
Port Qasim
21.05.2014
17.04.2015 22.12.2015
25.04.2018
47
CPHGC
29.06.2015
12.04.2016 26.01.2018
17.08.2019
50
Average
(months)
46
The fourth and last imported coal based power generation project which was conceived under CPEC is
300 MW Gwadar Project which holds strategic importance for Pakistan due to its location in the port
city of Gwadar which is turning out to be a gateway to progress and prosperity of not only Pakistan but
the entire region. The establishment of Gwadar Project is crucial to make Gwadar self-sufficient in
electricity, as it is currently relying on the 100 MW imported electricity from Iran. It will not only deliver
300 MW to the system but will also be instrumental in flourishing economic activities in Gwadar which
features heavily in CPEC and envisages to be a crucial link between the One Belt One Road and
Maritime Silk Road Project. After determination of tariff by NEPRA, Letter of Support (LOS) was issued
to the Project on 23rd August 2019 after which the project was formally inaugurated on 4th November
2019 in Gwadar. The inauguration ceremony was attended by Senate Chairman Sadiq Sanjrani, senior
officials of GoP including Power Division, Planning Division, PPIB and the members of high level
Chinese delegation. The project encountered delays on part of tariff determination, land acquisition,
signing of PPA, grid interconnection & transmission infrastructure issues which took long time in
settling. Such delays were beyond the reasonable control of project company/sponsors. Accordingly,
PPIB as facilitator played its due role, and with the combined efforts and support of all concerned
stakeholders, such issues were settled amicably and the project was put back on the track of
development. However, the COVID-19 challenge is feared to impact on the development of project.
Nevertheless, efforts are in progress to evade this natural calamity with little or no damage.
It goes without saying that imported coal plants have proved useful in bringing in the required
technology in the country, thus working as a catalyst to develop local coal based projects. Furthermore,
they have built the capacity of native human capital of the country for managing Thar coal supply
chain and its utilization for power generation in future. The imported coal plants are equipped with
super critical technology with state of the art intervention systems, which ensure mitigation of
hazardous coal emissions like NOx and SOx while adhering to strict criterion set by World Bank and
achieving values much below the local National Environmental Quality Standard.
In addition to imported Coal based Projects, RLNG projects were also conceived for providing relief to
the electricity starved system within a quickest possible time frame. In this regard, initially, three mega
projects were planned namely, 1,180 MW Bhikki, 1,223 MW Balloki and 1,230 MW Haveli Bahadur Shah,
all located closer to the load centers. The Government of Punjab decided to develop 1,180 MW Bhikki
Power Project in Bhikki, District Sheikhupura through its own budget and accordingly established
Quaid-e-Azam Thermal Power (Pvt) Limited (QATPL) while 1,223 MW Balloki and 1,230 MW Haveli
Bahadur Shah Projects were undertaken by the Government of Pakistan through a SPV National
Power Parks Management Company Limited (NPPMCL). PPIB processed these federal and provincial
government funded projects in IPP mode under the provisions of Power Generation Policy 2015. Later,
due to slippages in timelines of some advance stage projects which otherwise were scheduled to come
on line during 2017-18 (mainly Neelum Jhelum hydropower project), the GoP decided to launch
91
92
92View entire presentation