IEC Transmission Segment Development Plan 2023-2027
Additional events - cont.
חברת החשמל
Israel Electric
Collapse of the crane at Rothenberg site
■ On May 13, 2023, due to an extreme weather conditions, the crane of the coal pier at the site collapsed,
damaging the coal pier and killed 2 people. As a result of the collapse, the bridge was damaged and the
ability to unload coal at the pier was disabled.
■ As of April 10, 2023, IEC transports coal using trucks from the Orot Rabin site and also unloads coal at the
Port of Ashdod and transports it according to the needs of the Rotenberg site.
■ IEC operates to build a temporary bridge for the purpose of unloading coal at the Rothenberg pier, which is
expected to be completed at the end of 2023.
At this stage, it is not possible to assess the full impact of the event on the company's financial condition.
Source: IEC's Financial Statements for 2022FY and for H1.2023