Investor Presentaiton
ADDENDA
INFRAESTRUCTURA ENERGETICA MEJILLONES. "IEM"
Thermal contracted
+ port
US$1.0bn investment, within schedule and budget
Project
highlights
375MWe gross capacity =>
337M We net base-load capacity
• Pulverized coal-fired power plant
meeting strict environmental
standards
Mechanized port, suitable for cape-
size carriers
Scheduled completion date: 3Q18
IEM & port currently in
commissioning & testing phase
Ongoing
developments
US$1.0 billion investment
(US$764 million paid as of
3/31/18)
Financed on-balance sheet within
EECL
Engie Energía Chile Presentation to Investors - 1Q 2018
•
Main contracts
& Progress
ENGIE
•
Developed to supply distribution
companies
Turnkey EPC contracts:
IEM plant: SK Engineering and
Construction (Korea)
Port: BELFI (Chile)
Overall progress rate as of
Mar. 31, 2018: 95.4%
38