Actions Speak Louder – Coastal Virginia Offshore Wind

| CVOW Timeline Actions Speak Louder Dominion Energy® Sep. 2019 ✓ Dec. 2020 March 2021 March Mid 2021 - Mid 2021 Mid to Late 2021 Late 2022 Mid 2023 Late 2023 - 2024 - 2026 2.6GW project announced Construction & Operation Plan (COP) submitted to Bureau of Ocean Energy Management First set of virtual public meetings Continue public meetings and conduct surveys COP updated from public input and routing considerations Begin filing for other necessary permits / approvals Final decisions for necessary permits/approvals Begin construction of onshore transmission Construction of offshore components and remaining onshore transmission 15