Q3 and Q4 2023 Corporate Highlights slide image

Q3 and Q4 2023 Corporate Highlights

Skouries: Recent Achievements • • Full construction mode on the Company's next phase of growth * Q3 2023 Highlights Overall project process at 34%, expected to be ~48% by year end Engineering, procurement and contracting • • • Detailed engineering at 56% • • Procurement at 73% Construction • Site preparation and relocation of temporary facilities Mobilized contractor and commenced work on the primary crusher earthworks and pilings Underground Development Progress advanced on the west decline Process Facilities work in Q4 2023 • • Completion of structural steel and cladding of process plant Continuing primary crusher foundation construction eldorado gold Primary crusher foundation Open pit 10