Investor Presentaiton
•
•
•
•
•
Lihir Seepage Barrier Feasibility Study
Feasibility Study Status
Ground investigation completed in FY19
Current alignment utilises Harbour Waste Platform and
provides opportunity to access additional gold ounces
Cut off wall construction using clam shell and hydromill
Full scale construction field trials planned for H2 FY20
Completion of feasibility study and cost estimate Q1 FY21
New Seepage Barrier Alignment
Near Shore Cut Off Wall
Curre
ment Cut Off Wall
Sept 2018 Cu
AAAAA
SECTION
1:100
18107
SECTIONE
1.30
кото
NOT FOR CONSTRUCTION DRAFT
CHAPE
Legend
Near Shore Cut Off Wall (NSCO)
Sept 2018 Cut Off Wall
Current Alignment Cut Off Wall
0
100 200 300 m
Construction Equipment for Cut off Wall
Clam Shell
Hydromill Cutter
23
23View entire presentation