Sustainability Report ENEVA 2020
6.3.3 Azulão-Jaguatirica
Integrated Project
UPSTREAM + GAS-FIRED GENERATION
The Jaguatirica II TPP is being built in Boa Vista, state of Roraima,
and will have an installed capacity of 141 MW. The asset is expected
to start operating in the second half of 2021. Consumption of natural
gas produced at the Azulão Field, in the state of Amazonas, has 2P
reserves certified by Gaffney, Cline & Associates of 5.9 billion cubic
meters (bcm).
The input will be liquefied and transported by an existing road to
the plant using the logistics network currently used for diesel oil
transportation.
By starting the Jaguatirica II TPP operation, we estimate that a
significant part of the diesel-fired generation that supplies Roraima
will be displaced. This will allow for an approximate 35% reduction
in carbon emissions and 99% of NOx.
Our work in regions that are not connected to the National
Interconnected System (SIN), such as Roraima, provide energy
security and cost reductions by offering permanent power
availability.
ABOUT
LETTER FROM
ABOUT
FIGHTING
THIS REPORT
MANAGEMENT
ENEVA
COVID-19
INTELLECTUAL &
ORGANIZATIONAL
CAPITAL
SOCIAL &
MANUFACTURED
HUMAN
NATURAL
CAPITAL
CAPITAL
RELATIONSHIP
CAPITAL
CAPITAL
FINANCIAL
CAPITAL
APPENDICES
GRI
CONTENT
INDEX
SASB
CONTENT
INDEX
SUSTAINABILITY REPORT ENEVA 2020
PAGE 61View entire presentation