Established and Integrated Owned Infrastructure Allows
for Low Cost, Organic Capacity Expansion
Tabang infrastructure is complete, with discretionary low capex brownfield growth available if the environment is supportive
Capacity (Mtpa)
60+
Direct
BCT: 368km
69 km
Haul road
Tabang
Mine
Senyiur Jetty
Barging
94 km
Barging
BCT: 274 km
KFT-1/2: 256 km
BCT
Transshipment
KFT-1
30+
KFT-2
102 km
Haul road (1)
Barging
181 km
Barging
BCT: 288 km
Haul road(2)
24 km
Transshipment
Gunung Sari Jetty
Mahakam River
Port Facilities at
Muara Pahu
Barging
Today
Upside
Established mine to port infrastructure owned by Bayan. Haul trucks and barges owned / operated by trusted third party contractors
Notes
20-25 km
Haul road
Teguh
mine
Teguh (TSA)
Jetty
Barging
463 km
Wahana
mine
21-30 km
Haul road
Barging
20 km
Wahana (WBM)
Jetty
15-20 km
Haul road
Perkasa
mine
Perkasa (PIK)
Jetty
Direct shiploading to Handy / Panamax Vessels
Capacity (Mtpa)
40+
24
BCT
Today
Upside
8-10
Floating crane
Today
8-10
(1) Bayan is in the process of permitting and designing a haul road from the Tabang mine direct to the Mahakam River, which would allow Bayan to minimize its reliance on the seasonal rivers served by the Senyiur and
Gunung Sari Jetties, to barge our coal from the Tabang mine to BCT or floating transfer barges. Road construction is expected to complete in 2022.