NHPC Financial Highlights & Renewable Energy Projects
NHPC: Projects Under Construction
Project Under Construction-Subsidiary
एनएचपीसी
NHPC
29
Installed
NHPC Project
Capacity
(MW)
Design
Energy (MU)
Type of the
project
CCEA Estimated
Cost (Rs. Crore)
(Price Level)
Anticipated
Project Cost (Rs.
Crore)
Provisional
Project
Expenditure till -
Dec 22 (Rs.
Crore)
Expected
Commissioning
Schedule
Teesta-VI (4X125)
500
2400
Run of River
5748.04 (July'18)
5748.04 (July'18)
2,037.88
FY 25-26 (Q-2)
Sikkim
Rangit-IV (3X40)
120
508
Sikkim
Run of River
with small
pondage
938.29 (Oct' 19)
938.29 (Oct' 19)
400.84
FY 24-25 (Q-2)
Ratle (4X205+30)
850
3137
Run of River
5281.94 (Nov 18)
5281.94 (Nov'18)
188.46
FY 26-27 (Q-1)
UT of J&K
Total (C)
1470
6045
11968.27
11968.27
2,627.18
Total (A+B+C)
6434
24068
39099.02
60021.07
33,640.55View entire presentation