EA ЕВРАЗИЙСКИЙ Positive: Public-Private Partnership in Action ■ Flexible PPP contract structure allowed to fund money from banks and to receive support from the State Investment Fund ■ Close cooperation between stakeholders helped to adjust project parameters in line with economical environment Experience obtained during project preparation and implementation was used in other projects (Sochi, Krasnodar region) Negative: Lessons Learned Lack of supporting mechanisms from the public partner for loans security Change in tariffs policy at the federal level slowed down implementation of the project ■ Very difficult and expensive procedures of Vnesheconombank resulted in additional cost for the private partner 23.10.2014 12