Our initiatives for "New Normal" (3)
Daiwa HouseⓇ
Started development of Japan's largest data center to capture the demand for digitization,
given the progress in digitization among corporations due to COVID-19
| Air Trunk TOK1(Tokyo-one) Data Center
© 2020 Daiwa House Industry Co., Ltd. All rights reserved.
Location
Inzai city, Chiba pref.
(in Chiba New Town)
Total site area
Total floor area
Approx. 235,000m
Approx. 330,000m
From Oct. 2020 to 2030 (scheduled)
AIRTRUNK
Total construction
period
It is located on the Shimosa plateau which has a solid
ground
Japan's largest data center park (maximum 15 buildings)
The total floor area is 330,000 square meters, which is
equivalent to 7 Tokyo Domes
The maximum capacity of electricity that can be supplied:
600MW
Inviting an extra-high-voltage substation capable of
supplying up to 1,000 MW of electricity within the park.