cct Since we last met.. DATA CENTRES 2020 has been a challenging year and CDC has grown stronger in response to the testing environment without interruption or diversion from its strategic short term goals What we said we would do... ✓ Deliver Hume 4 and Eastern Creek 3; construction completed in November 2019 and September 2020 ✓ Bring 24MW of capacity to income production; delivered across Eastern Creek, Fyshwick and Hume ✓ Grow EBITDA run rate by 50% year on year; 50% achieved from FY2019 to FY2020 ✓ Extend debt facilities and improve terms; achieved along with greater flexibility for future growth ✓ Grow National Critical Infrastructure client base; further strategic clients secured in all key sectors ✓ Identify and pursue additional strategic opportunities; New Zealand expansion Eastern Creek 3 Hume 4 6