DATA CENTRES
2020 has been a challenging year and CDC has grown stronger in response to the testing environment without interruption
or diversion from its strategic short term goals
What we said we would do...
✓ Deliver Hume 4 and Eastern Creek 3; construction completed in November 2019 and September 2020
✓ Bring 24MW of capacity to income production; delivered across Eastern Creek, Fyshwick and Hume
✓ Grow EBITDA run rate by 50% year on year; 50% achieved from FY2019 to FY2020
✓ Extend debt facilities and improve terms; achieved along with greater flexibility for future growth
✓ Grow National Critical Infrastructure client base; further strategic clients secured in all key sectors
✓ Identify and pursue additional strategic opportunities; New Zealand expansion
Eastern Creek 3
Hume 4
6View entire presentation