MINING OVERVIEW
Underground operations
E48 first lift (E48L1)
-
Commissioning completed in mid-2011 (block caving method)
100% automated mining achieved in October 2015
E48 scheduled to be completed within EVN's FY24
E48 second lift (E48L2) is part of the LOM plan
Mining of E48 deposit will be stopped by end of December 2023 due to
faster than expected grade decline
E26
E26 mining areas comprised of L1, L2, L1N block caves and the E26SLC
Current mining is focused on E26SLC (commenced 2016) and E26L1N
block cave (commenced 2022)
E26SLC consists of 4 sub levels with 2 more levels under development
Evolution's potential LOM scenario
2
3
4
Equipment and site overview
SELF
Mining Operations Centre: Fully
automated mining focused on
safety and efficient mining
E48
Operations Centre
(mill, haulage, office)
2023 2026
Baseload Mining
E26L1, E26 SLC, Open Pits
& Stockpiles
2027-2031
E22 SLC option to
replaces Open Pits &
Stockpiles
2032 - 2042
Production is
Predominantly GRP314
& E26L3 Blockcaves
Evolution
MINING
2042 - LOM
E48L2 Blockcaves plus
Other Opportunities
E26
Headframe is centrally located amongst block cave suitable
deposits
34