Construction schedule - Origin 1
•
Origin 1-plant purpose
-
Produce CMF and HTC at commercial volumes
Produce CMF and HTC and other intermediates in volumes that allow customers to
qualify products and applications other than PET
Objectives - by end of Q3 2021
-
Achieve activities required to enable module lift by end of Q4 2021 DONE
Hire Process Automation Lead, additional Project Manager/ Project Engineer DONE
Objectives - by end of Q4 2021
-
-
-
-
Hire Origin 1 operating leadership: Site & Plant Director, Operations Manager, Site
EHS&S (Environmental Health, Safety, and Security) Manager DONE
Complete structural elements of plant ISBL and complete foundations of auxiliary
process buildings DONE¹
Erect main plant modules DONE
Install ENCON evaporator module system DONE (Previous: Receive ENCON
evaporator module system by end of Q1 2022)
Objectives by end of Q1 2022
-
Receive additional major equipment (tanks, etc.)
•
•
•
-
Piping fabrication start DONE (Previous: By end of Q2 2022)
Objectives by end of Q2 2022
1st round of operations hiring (Admin, Head of Shift Operators, Manufacturing
QA/QC Lead)
Objectives by middle of Q3 2022
-
Electrical installation start
Last major equipment arrives on site
Objectives by beginning of Q4 2022
First system turnovers to commissioning and start-up team
1. Does not include biomass storage unit.
Operations
Origin 1 Timeline (Detail View)
Capital Project
3Q2021 4Q2021 1Q2022
2Q2022
Detailed Engineering
Piping
Fabrication
Start
Install ENCON Evaporator System
(achieved vs original)
(achieved vs
updated vs
original)
Construction
Module Erection
(achieved vs updated vs original)
Organizational Design
Hire Operations
Leadership
Hire & Train Operations Staff
3Q2022
4Q2022 1Q2023
Last Major Equipment
Arrives On Site
Electrical Installation Start
Commissioning &
Start-Up
Start-Up
ORIGIN