Investor Presentaiton slide image

Investor Presentaiton

Monthly ITAAC Completions 55 45 40 40 35 30 25 20 15 Vogtle Unit 3 ITAAC Completion Forecast & Major Milestones 21 24 Total ITAAC Completed 275 Total ITAAC Remaining 123 15 36 35 37 O Start Fuel Load 210 180 150 Unit 3 In-Service 120 90 Blue Circles: December 2022 Benchmark 60 Milestone Dates ITAAC Remaining as of Month-end 10 10 5 0 11 4 6 3 12 103(g) Letter Received Oct-21 Nov-21 Dec-21 Jan-22 Feb-22 Mar-22 Apr-22 May-22 Jun-22 Jul-22 Aug-22 Sep-22 Actual ITAAC Completions Forecast ITAAC Completions Red Circles: March 2023 Benchmark Milestone Dates 30 0 Oct-22 Nov-22 Dec-22 Jan-23 Feb-23 Mar-23 Forecast ITAAC Remaining Schedule projects an in-service date as early as Q4 2022 with margin to Q1 2023 Milestone bars and lines represent the range of potential start dates for each milestone with the left side of each indicating currently targeted start dates under the December 2022 benchmark and the right side indicating start dates expected to be necessary for March 2023 benchmark 8