Key Infrastructure (4/5)
Bayan is currently constructing a new coal haul road and barge loading facility to facilitate the next level of expansion
Key Assets
Overview
Coal Haul Road
to Mahakam
River
(Under
Construction)
Mahakam River
Barge Loading
Facilities (Under
Construction)
14
Coal Haul
Road
ā In December 2019, the Company commenced
construction of a 101km all-weather coal hauling road
which will link the Tabang mine directly to the Mahakam
River
The road will be paralleled for the majority of this distance
by a public road that the Company is also constructing
The hauling road will have 7 bridges and over 150
culverts
The Company plans to utilise 200-220 mt payload double
trailers along this road to optimise its coal production
ā The road is scheduled to be completed in 2022
Barge
Loading
Facilities
The Company has commenced construction of the barge
loading facility on the Mahakam River
In the initial phase this will have 3 x 4,000 tph barge
loaders
The facility will also initially have 3 x Side Dump for the
receiving of coal trucks that will have 2 x 2000tph crushing
capacity each
There will also be 3 x 4,000 tph 5km overland conveyors
linking the side dumps to the barge loaders
This barge loading facility will be used to load 300' barges
with 7,500 8,000 MT
The facility will also include other supporting infrastructure
including a camp, mess, workshops, fuel receiving jetty
and fuel tanks