The Sector Reform Timeline
®
Gov' Decision on Reform
Done
Sale of Alon Tavor site
Done
Done
Sale of 'Ramat Hovav' site
Sale of 'East Hagit' site
In process
Sale of "Eshkol" site
In discussions
Layout for continued operation of Reading site (in accordance with
the Arrangements Law)
Done
Submitting a plan in Reading site for two
new CCGT, before depositing
Done
Separation of the System Management & PDT
חברת החשמל
Israel Electric
By year 2032
In process
In process
Prepared for
vacant
possession
In process
Construction of the first NG fired CCGT H (unit 70) at 'Orot Rabin' site
Construction of the second NG fired CCGT H (unit 80) at 'Orot Rabin' site
Transfer of 'Area D'
Re-examination of the supply segment
Stable
activation
Stable
activation
Pasulon trandring
subject to mil
standing in an agreement
Supply segment pilot Opening the electricity sector to full
T= 0
6/3/18
competition*
T=18
12/3/19
T=22
3/31/20
T=30 T=36 T=39
12/3/20 5/3/21 9/1/21
T=41
11/1/21
T=48: T=55 T=59
6/1/22 1/1/23 4/30/23
T=60
6/1/23
08/2022
* The Electricity Authority (EA) is expected to open the electricity sector to full competition starting January 1, 2023