Building the Large-Scale Gross Mine
Building the Large-Scale Gross Mine
Gross - Brief Overview and Summary
Location
Project parameters
Location
Infrastructure
Mine type
Stage
Start-up year
Average production
Construction cost
Russia, Yakutia
5 km from Neryungri operating mine,
accessible by all-season road
Open pit, Heap leach
Fully permitted, construction started in
June 2016
2018
200+ koz
US$250 million
LoM average AISC
US$760/oz
Project Highlights
Gross is the largest project in Nordgold portfolio – large resource
base for a mine with 200+ Koz production and about 17 years life of
mine
PAY
World class ore body: 9.7 Moz at 0.67 g/t in MI&I Mineral Resources.com
and 4.4 Moz at 0.72 g/t in Ore Reserves
Straightforward low cost heap leach metallurgy with high recovery
rate at about 82.5%
Project has excellent economics with the costs in the 1st quartile of
the cost curve and IRR of almost 40% at $1250 gold price
The successful pilot production confirmed heap leaching recovery
parameters and reduced execution risk
Gross project is on track to start operation in H2 2018
800DY
600 my
Gross project general view
Gross orebody model and open pit, long section
☐ <0.4
0.4-0.8
☐ 0.8-1.2 Au
25
1.2-1.6 g/t
1.6-2.0
>2.0
12
nordgold
more than goldView entire presentation