PTTEP Project and Financial Overview
Transition | G1/61 and G2/61
Note: ARAA Asset Retirement Access Agreement
ATA Asset Transfer Agreement
OTA
PSC
SAA
Operations Transfer Agreement
Production Sharing Contract
Site Access Agreement
Operatorship transfer completed
G1/61 - Erawan
Initial production rate 200-250 mmscfd
Sole Investment 100%
2019
G1/61, G2/61 PSC signed
G1/61 OTA, SAA,
ARAA signed
G1/61 Prelim Facility
Access Agreement signed
G2/61 ATA Signed
2020
2021
2022
G1/61 Site Access Delay -
G2/61 - Bongkot
Transition of 200mmscfd completed
Proceed for additional 500mmscfd in Mar 2023
Production rate 700mmscfd
G1/61, G2/61 Petroleum sales agreements signed with PTT
G1/61, G2/61 PSC
effective 24APR202
G2/61 Transition PSC
remaining areas
G1/61 reaches
800mmscfd
2023
- G1/61 Preparation and Production Ramp-up -
2024
2025