PTTEP Project and Financial Overview

Transition | G1/61 and G2/61 Note: ARAA Asset Retirement Access Agreement ATA Asset Transfer Agreement OTA PSC SAA Operations Transfer Agreement Production Sharing Contract Site Access Agreement Operatorship transfer completed G1/61 - Erawan Initial production rate 200-250 mmscfd Sole Investment 100% 2019 G1/61, G2/61 PSC signed G1/61 OTA, SAA, ARAA signed G1/61 Prelim Facility Access Agreement signed G2/61 ATA Signed 2020 2021 2022 G1/61 Site Access Delay - G2/61 - Bongkot Transition of 200mmscfd completed Proceed for additional 500mmscfd in Mar 2023 Production rate 700mmscfd G1/61, G2/61 Petroleum sales agreements signed with PTT G1/61, G2/61 PSC effective 24APR202 G2/61 Transition PSC remaining areas G1/61 reaches 800mmscfd 2023 - G1/61 Preparation and Production Ramp-up - 2024 2025 ->