Recommendation for site specific auction design ||
Auction design features
Prequalification for Bidders
Open for prequalified Bidders
Explanation
Prequalification requirements enable participation of serious Bidders / Investors, on the
basis of developed project plan and obtained licenses
Only Bidders / Investors that pass prequalification process are invited to participate in
auction
Requested submission of bid bonds
Bid bond is secured by Bidders with objective to prevent non-installation
Retention of bid bonds for penalization
In case of non-installation or delay in installation, bind bond is retained. Bid bond amount
should be in range 1.5 - 2% of average upfront investment cost calculated per kW
Lead time for finishing installation
It is recommended to be two years, from the end of auction. In case there are known grid
connection problems and delays in licenses, this period should be extender for half a year