Major milestones of Mid-and-Long-Term Roadmap
Some of the milestones that were set in 2019 have already been achieved.
Major milestones
Contaminated
Reduce to about 150 m³/day
water management Reduce to about 100m³/day or less
Stagnant water
removal /
treatment
Fuel removal
Fuel debris
retrieval
Waste
management
Revised Roadmap
Within 2020
achieved
Within 2025
achieved
Complete stagnant water removal / treatment in buildings* Within 2020
Excluding the reactor buildings of Units 1-3, Process Main
Buildings, and High Temperature Incineration building.
Reduce the amount of stagnant water in reactor buildings
to about a half of that in the end of 2020
Complete of fuel removal from Unit 1-6
Complete of installation of the large cover at Unit 1
Start fuel removal from Unit 1
Start fuel removal from Unit 2
Start fuel debris retrieval from the first Unit
(Start from Unit 2, expanding the scale gradually)
Technical prospects concerning the processing/disposal
policies and their safety
Eliminating temporary storage areas outside for rubble and
other waste
FY2022 2024
Within 2031
Around FY2023
FY2027 2028
-
FY2024 2026
Within 2021
Around FY2021
Within FY2028
Revised to
second half of
FY2023
achieved