Renewable Energy Projects Under-Construction
2.5 GW Under-construction Projects
SECI: Wind Projects Tamil Nadu: 1,260 MW
SECI IX (810 MW) + SECIX (450 MW)
Signed 25-year PPA with SECI
Commissioning: progressively from Q1 FY23
Blended tariff
Capex
Group Captive: Wind & Solar Projects Karnataka: 825 MW
PPA
Solar 225 MW; Wind: 600 MW
Signed 25-year PPA with JSW Steel
Commissioning: Solar - from Q4 FY22 (Solar), Wind -
progressively from Q1 FY24
Group Captive: Wind Project Maharashtra: 95 MW
Signed 25-year PPA with JSW Steel
Commissioning: progressively from Q4 FY23
Land &
Resources
Transmission
•
Equipment
JSW Energy
3.08/unit (excl. hydro)
•Total: 16,660 Crore
Committed: 7,000 Crore,
including a spent of ~1,660
Crore
Signed for 2.2 GW
Acquired/Locked-in
Construction progressing well
for dedicated transmission
lines for all projects
• 1.4 GW wind turbines
ordered Delivery to start in
Q1 FY23
1993 MW
225 MW
240 MW
I Map for illustrative purposes, showing project locations
Group Captive: Wind Project Tamil Nadu: 38 MW
Signed 25-year LT PPA with JSW Steel
Commissioning: progressively from Q4 FY23
Kutehr Hydro Project Himachal Pradesh: 240 MW
3x80 MW Run-of-the-river Hydro Power Plant
PPA under finalization with Haryana Discom
Commissioning: September CY24
☐
Expected
Commissioning
FY22: 100+ MW
FY23: 1200+ MW
FY24: 700+ MW
FY25: 240 MW (Kutehr)
Modular/phased
commissioning to provide
accelerated cashflow
generation
JSW Energy Investor Presentation