Investor Presentaiton
Offshore wind build-out plan
Installed capacity
MW
Under construction
Awarded
2,852
22,224
1,045
1,498
3,214
1,628
920
11,987
1,166
130
900
8,871
Installed
capacity
Q1 2023
Greater
Changhua
German
Portfolio¹
South
Fork Wind
1 & 2a
Greater
Changhua
2b & 4
Country
Taiwan
Germany
US
Taiwan
Expected
completion
2023
2024/2025
2023
2025
Construction
status
Decided
(FID'ed) and
US North-
East cluster2
US Mid-Atlantic
cluster³
Baltica 2
Baltica 3
Hornsea 3
Decided
(FID'ed),
installed
installed and
capacity
awarded
capacity
US
US
Poland
Poland
UK
2025
2025/2026/
2029
2027
By 2029
2027
Pending FID
Pending FID
Pending FID
Pending FID
Pending FID
Delayed
On track
On track
On track
Turbine
111 x 8 MW
Siemens
Gamesa
106 x 11 MW
Siemens
Gamesa
66 x 14 MW
16
12 x 11 MW
Siemens
Gamesa
107 x 14 MW
Siemens
Gamesa
1. German Portfolio: Gode Wind 3 (253 MW) and Borkum Riffgrund 3 (913 MW); 2. Revolution Wind (704 MW) and Sunrise Wind (924 MW); 3. Ocean Wind 1 (1,100 MW),
Skipjack 1 (120 MW), Skipjack 2 (846 MW) and Ocean Wind 2 (1,148 MW)
OrstedView entire presentation