Northland Power Corporate Presentation
Asia Offshore Wind Development
Taiwan | Hai Long 1.0 GW
•
•
•
.
Executed majority of the key contracts for the project
Signed 15-year Turbine O&M with OEM (Siemens Gamesa)
Will deploy Siemens 14 MW Turbine (recently certified)
Major construction programs running as planned
•
•
Commenced early construction work/fabrication of key components
Kicked off in-water construction and made substantial progress on fabrication of
materials and advancing on lead order items (offshore & onshore substations
and jackets).
Signed strategic sell-down partnership with Gentari for 49% interest of Northland's
60% interest in the project
HL3
HL2
Taiwan
Taipei
City
Project Name
Capacity
PPA¹ Rate (NTD1/kWh)
Yrs 1-10: 6.2795
Hai Long 2A
294MW
Yrs 11-20: 4.1422
Hai Long 2B
224MW
30-year Corporate PPA
Hai Long 3
504MW
Hai Long timeline
1. NTD represents New Taiwan Dollar.
2021
2023
2023
2026/2027
0
NORTHLAND
POWER
Project design
and
optimization
Achieve
Financial Close
Expect
to start
Construction
Expected
Commercial
OperationsView entire presentation