Edmonton Terminal - Overview
Attractive terminal position with three tanks under construction
■Long-term MSA in place with principal customer at the terminal that also contemplates the potential future sanction of additional infrastructure on
a fixed-fee basis and 25-year term
Biofuels blending project sanctioned under the MSA and placed into service in Q2 2022
■ Constructed 1 x 435kbbl tank for new investment grade energy customer and placed into service in Q3 2023
Constructing 2 x 435kbbl tanks for investment grade, senior oil sands customer for late 2024 in-service
RAIL LINE
2 x 435kbbl Tank Under Construction
2024 in-service
COLD LAKE
EDMONTON
TERMINAL
RAIL LINE
SUNCOR
REFINERY
AOSPL
KML / ENB
Connection
Waupisoo
and Access
Inbound
COLD LAKE
Essential Location
■Located at the heart of the Edmonton Industrial Area
■ Next to two major refineries
■ Have land position to add up to ~1.0mmbbl of tankage
beyond tanks currently under construction
GIBSON ENERGY INVESTOR PRESENTATION
18
IMPERIAL
REFINERY
PEACE
PEACE
COLD LAKE
ACCESS
CORRIDOR
WAUPISOO
Trans Mountain
Connection (1)
TRANS MOUNTAIN
TRANS MOUNTAIN
EXPANSION
(1) Trans Mountain Connection easily modified to connect to Trans Mountain Expansion once operational.
ENBRIDGE
MAINLINE
Flexible Egress Access
■ Near both major egress pipelines (Enbridge and Trans
Mountain/TMX) (1)
Access to both CN/CP rail lines
Flexibility to offer both crude oil or refined products storage
as well as inbound/outbound terminalling to customersView entire presentation