ALBERTA POWERLINE
Fort McMurray West 500 kV Transmission Project
The design and planning phases
were completed and
construction commenced in
August 2017.
Tower assembly is proceeding
ahead of schedule and line
stringing is proceeding on
schedule.
The target energization date of
June 2019 remains on track.