Concrete weight coating plant commissioned at Nanakapaya - Port Mundra
Commissioning of 3rd Coating plant at Samaghogha, Mundra.
Commissioning of 3rd Pipe mill manufacturing LSAW Pipe using JCO forming process in
Samaghogha, Mundra with capacity of 250,000 M.T P.A
Commissioning of 4th Pipe mill manufacturing HSAW (Spiral) Pipe at Samaghogha, Mundra
with capacity of 150,000 M.T P.A
Start up of Integrated Pipe Unit Ductile Iron Pipe manufacturing plant of 200,000 MT per
annum capacity along with Blast Furnace of 250,000 MT per annum capacity and a Coke
Oven Plant.
Commissioning of 5th & 6th Pipe mill manufacturing HSAW (Spiral) pipe at Bellary-
Karnataka and Samaghogha-Mundra with combined capacity of 390,000 M.T P.A.
2nd Induction bending plant commissioned at Samaghogha, Mundra.
Commissioning of 7th Pipe mill manufacturing LSAW using JCO forming in Nanakapaya -
Port Mundra with capacity of 300,000 M.T P.A.
Commissioning of 8th Pipe mill manufacturing HSAW (Spiral) pipe at Kosi Kalan, Mathura, U.P
with capacity of 150,000 M.T P.A. This mill is commissioned to cater to the water sector.