Healthcare Network P&L Statement and Expansion Projects
3
MAX
Healthcare
Status of ongoing expansion projects
Dwarka - 300 beds
MAX
Application of OC has been submitted in October.
Majority of the MEP and interior work are complete.
Lift installation and other finishing work are in
progress.
Expected commissioning by end of Q4 FY24, subject to
developer obtaining the OC.
Mohali - 190 beds
Nanavati - 329 beds in Phase I
All statutory approvals to start the construction have
been received
•
•
D-wall is completed and excavation work is underway.
EPC contractor has mobilized people on site.
•
Design development is in progress and the project is
largely on time.
Excavation and raft work are complete.
Steel fabrication up to ground level and slab work have
also been completed.
Ground level structure is expected to be completed in
Q3 and the project is largely on schedule.
Sec. 56, GGN - 300 beds in Phase I
Saket Complex (Max Smart) - 350 beds in Phase I
Saket Complex (Vikrant) - 300 beds in Phase I
Saket (East & West)
Max Smart
Phase I
MAX
Vikrant
D-wall has been completed and site excavation is
nearly done.
EPC contractor is on board and design development is
under progress.
TDR approval for additional 0.5 FAR has been received.
•
The process of transplanting the trees has been
initiated, which are on the critical path.
The work on project will start in December 2023.
Environmental Clearance has been received from the
State Level Environment Impact Assessment Authority.
Submission of drawings on Municipal Corporation of
Delhi (MCD) portal is in process.
17View entire presentation