Investor Presentaiton
INDUSTRIAL AREA OF BULUMINUNG
PEMPROV
KALTIM
AREA OF BULUMINUNG-GERSIK-LANGO BEACH
INDUSTRY OF 5,300 HA
ESTIMATED NEEDS OF ELECTRICAL POWER
Allocation
Land Areas
(Ha)
710
Electrical Power
(MW)
113,6
35
ES D
Pun Dung f
AGRICULTURAL PROCESSING
INDUSTRY ZONE
OIL AND GAS PROCESSING
958
153,3
INDUSTRY ZONE
MINING PROCESSING INDUSTRY
861
137,8
Pacada fecue T
ZONE
TRANSPORT & MACHINERY
1060
169,6
INDUSTRY ZONE
FOREST PRODUCTS PROCESSING
1118
178,9
INDUSTRY ZONE
SUPPORTING FACILITIES AREA
352
42,2
TOURISM AREA
9
1,1
PORT AREA
162
19,4
WAREHOUSE AREA
192
23,0
TOTAL
5.422 Ha
838,92 MW
Source: Buluminung Industrial Development Master Plan, Gersik, Lango Beach
So, the need for electricity for Industrial Estates is ± 838.92 MW which
requires around 18 substations with a capacity of 48 MW eachView entire presentation