PNRR: role of FS Group and financial resources
PNRR consists of six Missions. Each Mission consists of several
Components
Mission 3 - "Infrastructures for Sustainable Mobility" amounts to
around € 31.5 bn.
RFI acts as implementing body/subject of
Mission 3 - Component 1
Others operating Group's companies could
be beneficiaries of the PNRR as
implementing body/subjects.
Mission 3 - Component 1 "Investments on Rail Network" amounts to €
27.97 bn invested both on railways and on roads.
Upgrades on National Rail Infrastructure will pertain both HS network and
conventional rail network with infrastructural and technilogical investments (i.e.
ERTMS).
ANAS acts as implementing body of Mission
5 and in the project «Safe Roads>> together
with all others roads' concessionaires.
f
M3. INFRASTRUTTURE PER UNA MOBILITÀ SOSTENIBILE
M3C1 - RETE FERROVIARIA AD ALTA VELOCITÀ/CAPACITÀ E STRADE
SICURE
PNRR
(a)
React EU
(b)
Fondo
complementare
(c)
Totale
(d)=(a)+(b)+(c)
24,77
0,00
3,20
27,97
M3C2 - INTERMODALITÀ E LOGISTICA INTEGRATA
0,63
0,00
2,86
3,49
25,40
0,00
6,06
31,46
Note: in column a) may be found resources of Recovery and Resilience Facility
Informazione pubblica
F
Totale Missione 3