Feed-in Tariff Mechanism Elements Payment Coverage Provisions under the RE Act, IRR & FIT Rules •Guaranteed, on a fixed rate per kWh •Emerging technologies- biomass, solar, run-of-river hydro, ocean and wind, excluding generation for own use •For projects which enter into commercial operations after effectivity of the FITs with certain exceptions for existing plants •On-Grid areas only Mandated duration •Initial FITS- 20 years; Minimum - 12 years Connection to Grid Dispatch •Priority connection, purchase, transmission and payment by grid system operator ⚫NGCP to determine maximum penetration limits for intermittent Res •PEMC and NGCP to implement technical mitigation & improvements to ensure reliability of transmission •Priority and must dispatch 18